Injection

Lift Pit Leakage Treatment

Standing water accumulating in two lift pits, with ingress at the base slab to wall junction.

Location

Al Nahda, Dubai

Property Type

Commercial Building

Service

Injection

System

PU injection resin, crystalline cementitious tanking

Initial Condition

What We Found

Standing water accumulating in two lift pits, with ingress at the base slab to wall junction.

Scope of Work

What Was Carried Out

Dewatering, joint preparation, PU injection at the kicker joint, application of cementitious tanking to the pit interior.

HAVEN FORCE Solution

How It Was Solved

The kicker joint was injected to stop active flow, then the pit was tanked internally to provide a continuous secondary barrier.

Materials / System

PU injection resin, crystalline cementitious tanking

Project Gallery

On Site

Lift Pit Leakage Treatment — site photograph 1
Lift Pit Leakage Treatment — site photograph 2
Lift Pit Leakage Treatment — site photograph 3
More Work

Related Projects

WhatsApp Call Us